construct - An additional Stormwater Storage Tank • A new inlet works • Three Primary Settlement Tanks • Three new Aeration Tanks • Four new Final Settlement Tanks • The decommissioning and demolishing of two existing Final Settlement Tanks • Two new Tertiary Filters • A Sludge Storage Tank for primary sludge • An additional centrifuge for Sludge Dewatering • Minor chambers and sumps • Odour control measures • Solar PV panels • A Biodiversity Enhancement Area • Ancillary infrastructure as follows: o A new 2.4m high security fence o Site lighting o Internal roads and footpaths o Control and automation upgrades o An electrical supply upgrade
Reference: 2560317
| Received: | 26 May 25 |
| Decision: | 13 February 26 |